LIVERMORE — Selectpersons have decided to move forward with an arch-style design for a sand and salt shed, after discussing the pros and cons with an engineer and state officials.

Engineer Scott Braley of Plymouth Engineering, the company hired to design the shed, will complete the plans using the cost-saving measures discussed. After a final review by the board, the plans will be sent to the state and the bid process started. Other steps include applying for a loan and holding a special town meeting to approve the project.

The town is on a state list of municipalities that have salt leaching into the ground. Without a new shed, the town will lose its contamination waiver and be required to get a Maine Department of Environmental Protection license.

The Maine Department of Transportation would reimburse the town 37 percent of costs if it submits preliminary plans before the end of June. A construction loan at 1.5 percent interest is available through the DEP.

A month ago, the project stalled when estimated costs to build a laminated, wooden, arch-style building for 3,600 yards of sand and salt came in at $100,000 more than expected. The arch design was chosen because it is less labor intensive to build and was recommended by Peter Coughlan, director of the Community Services Division of the Maine Department of Transportation.

Selectpersons approved seeking up to $400,000 while they considered options. Actual costs won’t be known until the project goes out to bid. 

Advertisement

On Tuesday, Administrative Assistant Carrie Castonguay, Treasurer Amy Byron and Selectpersons Tom Gould, Tim Kachnovich, Megan Dion and Peter Castonguay met with Braley. Also attending were Coughlan, DEP Assistant Environmental Engineer Project Manager Brandy Piers, and local contractor Doug Gordon of Gordon’s Excavating.

Braley said he had the same sticker shock as selectmen when he received the construction estimate of $400,000. He used a similar project from a few years ago when estimating $300,000 for Livermore’s shed. Material costs have risen considerably since then, he said.

Piers said everything the DEP has financed and done with the MDOT has favored the arch design. She said the program won’t fund a fabric building for 20 years, because the salt creates a corrosive environment. “In 10 years you’ll be in the same boat again,” she said.

Coughlan warned of being penny-wise and pound-foolish.

“Think of the life of the building: You want it to last 30 to 40 years with as little maintenance as possible,” he said.

Gould said he appreciated Coughlan’s viewpoint but, “we’re a small town. $400,000 is a hard sell to a community this size.”

Advertisement

“Based on the financial information, two payments of roughly $12,000 would be needed each year,” Piers said.

“That’s less than a truck payment,” Byron said.

Coughlan said the town would receive the 37 percent reimbursement within a couple of weeks of receiving the construction plans from the engineer.

Piers suggested savings could come from moving the site of the shed a little to reduce the groundwork needed. Having Public Works do much of the site preparation and not putting in the second door would further cut costs.

Braley said one thing raising costs is the new utility pole which limits where the shed can be positioned. A lot of earthwork is included in the estimate. Eliminating some of the fill would also lower costs.

Coughlan said the shed would offer benefits that include salt not leaching away and less material wasted.