HARTFORD — Road Commissioner Jeremy Johnson is harvesting some big boulders from underneath Ricker Hill Road, along with old fence posts and a handmade logging chain also used as fill decades ago. Getting all that material out is expected to provide smooth driving ahead, he said.
“In the early ’50s, a rock wall that once stood beside this road was
pushed into the low area of the road, along with fence posts that still
held the whitewash and fencing,” excavator operator David Bragg said. “Over the years it was just paved over
and the rocks have been coming up ever since,” he said as the excavator dislodge rocks 4 feet below the old road surface. Some were too big to lift into a dump truck so they were put aside.
“The rocks are what makes our roads almost impassable in the spring,” Bragg explained. “They maintain moisture underneath, which freezes and pushes the rocks up to the surface in the spring. This is why rural Maine roads are so full of pot holes in the spring thaw.”
Rebuilding about 3,100 feet of the road, which runs between Route 140 and Jordan Road, is costing the town about $138,000. It has been in the planning stage for nearly two years.
“This project is not a Band-Aid,” Johnson said. “We want to keep the
road passable using the best road construction method possible. Reconstructing a road is more costly for towns on the onset, but it
should save the town money in the long run as a rock-free base will
make the road last much longer.”
After ditching and installing culverts along the road, the old surface was ground up with gravel and set aside. It will be used as part of the new gravel road base before it’s paved.
He said he’s grateful to Oxford Networks and Central Maine Power Co. for moving their buried cables to overhead locations in the construction area. “This made our job much easier,” he said.
An excavator loads one of the many rocks from underneath Ricker Hill Road in Hartford into a dump truck. Workers have found huge boulders, old fence posts and a handmade logging chain that were apparently used as fill for the road in the 1950s.
Hartford Road Commissioner Jeremy Johnson stands beside one of the large rocks dug out from under Ricker Hill Road. Workers have found lots of boulders,
old fence posts and a handmade logging chain that were apparently used
as fill for the road in the 1950s.