GORHAM, N.H. – Reconstruction work started Wednesday on the parking lot at the Pinkham Notch Visitor Center in the White Mountain National Forest.
The parking lot serves a complex of facilities operated by the Appalachian Mountain Club under a special use permit. It also serves several trail heads, including the popular Tuckerman Ravine Trail up Mount Washington.
Sections of the lot, which is a former roadbed for New Hampshire Route 16, will be cordoned off through late June or early July, according to the U.S. Forest Service.
This will affect access to trails and facilities at the popular site between Gorham and Conway.
“This project only affects one trail head out of hundreds across the forest, so people should absolutely not forego hiking in the Whites while construction is under way,” Dave Neely, assistant district ranger with the WMNF’s Androscoggin Ranger District, said by e-mail early Wednesday afternoon.
He said the parking lot, which can hold 285 cars, will not be closed during the project.
“The contractor clearly recognizes the importance of public access to this area during construction,” he added.
However, its capacity will be reduced to about 200 cars on any given day due to reconstruction work.
Citing the project’s impact on Pinkham Notch visitors, Neely said that during a peak weekend in April and May, spring skiers hiking in to Tuckerman’s Ravine will try to park from 600 to 800 cars there or nearby.
“On a particular Saturday in April last year, we estimated we had 4,200 people in the ravine and the car count was more than 800,” Neely said. “We’ve had people parking as far down as Glen Ellis Falls and as far north as Wildcat Mountain’s C parking lot.”
During construction, people can park in the lot or off the road in nearby overflow parking areas, which are actually the old roadbed.
“The shoulder is posted for no parking, and we ask people to respect that, largely for public safety and to protect the shoulder of the road,” Neely said.
The project will affect people trying to park as close as possible to access trails to the ravine, Old Jackson Road, Lost Pond Trail, and the bottom of Sherburne and Gulf of Slides trails.
To minimize disruptions to the public, there will be no construction on weekends or federal holidays.
The parking lot is a former roadbed of New Hampshire Route 16 prior to its relocation during the 1960s. It was never intended for its current use, Neely said. The project is designed to improve the visual appearance of the lot, provide for visitor safety, and protect natural resources while accommodating a similar number of vehicles at peak use times, he said.
“It’s exciting. It’s been a long time coming,” Neely said.
The lot’s capacity is being downsized to better facilitate a safe flow of traffic while maximizing efficient use of space and aesthetics, he said.
A trail will connect the pedestrian bridge over Ellis River to the south end of the lot. Also included in the design is a combination of paving and landscaping in the lot’s central part, while gravel surfacing at the north and south ends will be maintained.
Later this summer, additional planning will address overflow lots south of the visitor center, which require visitors to cross Route 16 in the 55 mph section, Neely said.
For more information, contact the Androscoggin Ranger District at 603-466-2713 or visit www.fs.fed.us/r9/white.