FRYEBURG – Poland Spring Water Co. has begun building a water-trucking facility on Route 302, about three-and-a-half years after the project was first proposed.
The Maine Supreme Judicial Court recently issued a ruling allowing Nestle Waters North America, the parent company of Poland Spring, to go ahead with its plans to build the facility. The proposal was first made to the Fryeburg Planning Board in August 2005, and had been debated in the local government and court system since then.
The facility will be used to load trucks with spring water piped in from extraction points in neighboring Denmark. It will service up to 50 trucks a day and be operational 24 hours a day. The site is approximately -mile west of the blinking light at the intersection of Route 302 and Denmark Road.
Mark Dubois, natural resource manager with Poland Spring, said the facility will cost about $2.1 million to build. The company will also add a second extraction site and an additional pipeline in Denmark.
“In total, it represents about $4 million of investment in the Lakes Region,” Dubois said.
The facility has drawn criticism from the group Western Maine Residents for Rural Living. Opponents have argued that the site does not conform with zoning rules for eastern Route 302, and that the facility will increase traffic hazards, noise and pollution.
The Planning Board initially granted a permit for the project, but it was overturned by the Board of Appeals. The matter was taken to the Oxford County Superior Court, but remanded back to the Planning Board to determine if the facility constituted a low-impact use.
After both town boards upheld the permit denial, the matter again returned to the Superior Court before being taken to the Supreme Judicial Court. A March decision allowed Poland Spring to proceed with the project.
Dubois said the facility will be set back in the woods 250 feet from the road, and take up four acres of a 59-acre parcel. He said the rest of the parcel will be public space for recreational uses such as snowmobiling and hunting, and will be added to contiguous parcels in Denmark and Fryeburg to create 750-acre areas of public land.
Dubois said acceleration and deceleration lanes will be added to Route 302 near the facility to accommodate trucks entering and leaving the site, and a wood and steel barrier will be constructed around the facility to dampen noise.
Dubois also said the average number of trucks will likely be about 30 per day. He said the company will operate a maximum of four trucks per hour from the station, and be limited to two trucks during times when school buses and evening commuters are on the road.
“Effectively, the facility’s going to serve one to two trucks per hour so it probably won’t affect us much,” he said.
The project is expected to take four to six months to complete, with 90 percent of the construction work force coming from Maine. Dubois said additional time will be needed to approve the water source with out-of-state distributors, and that the facility will likely go online in the first or second quarter of 2010.