WILTON – The Canal Street Bridge is on the Maine Department of Transportation’s list to be removed, and there’s a slim possibility it might help pay for a new one, selectmen were told Tuesday.
Selectman Paul Gooch, Town Manager Rhonda Irish and state Rep. Tom Saviello, U-Wilton, met recently with Chip Getchell of the state bridge maintenance division and told him why the bridge was needed, Gooch said.
Boats and ice shacks travel across the bridge from Main Street to the boat landing on Wilson Lake, Gooch said. Access from High Street behind the Bass Building and through the parking lot would be difficult to maneuver while hauling a boat, and there is no room to widen the road with the building on one side and a bank and homes on the other, Gooch said.
Another point the group plans to mention when Getchell comes to Wilton on April 3 to inspect the bridge and boat access is concern about fire safety without a way to exit the parking area in case of a fire, Irish told the board.
Getchell did provide some options to be considered for replacement bridges for $100,000 to $110,000, Gooch said. The town could incur another $100,000 expense if it has to remove the bridge.
When asked if there was a slim possibility of getting off the DOT removal list, Gooch responded no, but there is a very slim possibility that the state might provide some funds to replace it.
“It’s not safe,” Gooch said. “It has to come out. It won’t fall down tomorrow but it has to come out.”
The piers or abutments of the bridge are in good shape, he said.
The bridge has been in place since the previous bridge washed out in a flood in 1953, Selectman Norm Gould said.
Gooch believes that while the bridge will be removed within the year, he thinks the state would not take it out until the town has something to replace it.
Comments are no longer available on this story