RUMFORD – The nearly $6 million construction project to build a brand-new, modern wing of Rumford Hospital is expected to be completed by the planned Dec. 7 open house.
The 18,000 square feet of new space is the third and final phase of a major, more than $10 million project that has taken place during the past several years.
“This is the culmination of the renewal of Rumford Hospital,” said hospital spokeswoman Jane Bubar as she and the hospital’s facilities manager, Doug West, walked through the new wing Friday afternoon.
The small, rural hospital is a member of the Central Maine Medical Family and is affiliated with Central Maine Medical Center in Lewiston.
The decision to renovate much of the facility and to make a major addition to house most of the direct medical care came about after local residents made it clear several years ago that they wanted their hospital to stay in town and not move to a location along the highway.
During the past several years, a new, rounded entrance was built; most of the infrastructure was replaced; the emergency room totally remodeled and redesigned; a helipad constructed; and now, a new wing built.
“Patient comfort is the bottom line,” said West. “Everything is ADA compliant, and there are areas (in the patient rooms) for families to stay.”
Each of the new patient rooms – 16 private, two semi-private, and several postpartum – have bathrooms and showers and year-round temperature controls.
The rounded look of the new entrance is followed throughout the addition.
New nursing stations have been located to best serve a particular section of the wing, and the central nursing station even has a skylight.
A solarium for families of patients to gather extends toward the site of the helipad and over a new entrance for transporting patients from the helicopter into the hospital.
The new birthing center will be equipped with a birthing tub. The walls of the patient rooms are painted gentle shades of green, blue and beige, gentle peach adorns some of the nursing station walls, and the floors are wood-toned, made from a wood and clay composite.
Warren Allison, project superintendent for general contractors Ledgewood Construction of South Portland said many of the nearly 20 subcontractors have come from the River Valley area, including Waugh’s Mountain View Electric, which did all the electrical work.
Ground was broken, quite literally, considering the large amount of ledge discovered at the side and rear of the hospital, in January of this year.
“We’re on target,” said Allison of the planned December opening.
The original hospital was built in 1926. Major renovations or additions were made in 1965 and 1970, before the most recent one began a few years ago.
The space in the original building will eventually be used for medical-associated offices, but not for anything clinical, said Bubar.
West has been pleased with the way the nursing staff has adjusted to all the changes they’ve had to make while caring for patients.
“They have been exceptional through this and adapted to change, moved when needed,” said West.
The new ground floor will be used for storage, offices, and replaces and enlarges one operating room.
Along with 18,000-square-foot of new space, Phase III also included renovation of more than 7,000-square-feet of the existing building.
The open house on Dec. 7, will be an opportunity for community members, as well as everyone associated with the construction of the new wing, to see the final result and to celebrate the many years of effort it has taken to complete the modern update of the hospital.