FARMINGTON – Sixty-four SAD 9 voters unanimously approved the design and layout of the proposed new W.G. Mallett School in a straw vote Thursday.

The vote followed a high-tech presentation by architect Stephen Blatt and his associates.

In a straw poll in June, voters approved building on the same site as the present school.

The next step includes state Board of Education approval of the design in October followed by a referendum on the project tentatively set for Nov. 20.

The proposed 60,000-square-foot brick school plan now referred to as “the dog,” because the design resembles a dog, Blatt said, is 20,000 square feet larger than the present Mallett School.

“With the cafeteria and gymnasium close to the front door, the school can serve as a community building as well as a school,” he said, indicating the classroom section can be closed off for night meetings with everyone entering the front door.

Buses circle a loop from Middle Street to drop off or pick up students near a covered front porch. A separate drive with parking spaces for parents to bring children to school also enters from Middle Street, goes around the school and exits on Quebec Street, he said.

The design allows space for prekindergarten and kindergarten classes on the first floor as well as a music and computer room while first, second and third grade classes are on the second floor.

The design of each room includes a large set of windows and smaller windows for maximum daylight harvesting, Blatt said. Room for a wood pellet silo and boiler were drawn into the plans.

Once the school is built, the present school will be razed and the space turned into a large playground.

Most of the few questions asked covered parking around the school. The design gives more parking spaces than the current school, Assistant Superintendent Susan Pratt assured voters. The plan provides about 100 parking spaces including 20 for the University of Maine at Farmington. Spaces are also planned along the drive from Middle Street around the school and exiting on Quebec Street.

Without buses in the bus loop, Blatt said, there are an additional 28 spaces within the loop available for night meetings.

The potential for adding a future greenhouse was questioned. The flat room above the school entrance and cafeteria could be converted to a green roof, Blatt said. The building is designed to be Leadership in Energy and Environmental Design certified, he added.