3 min read

CANTON – Selectmen were presented Thursday night with agendas for three hearings on the controversial village relocation project, which townspeople have rejected funding three times.

The longstanding project was initiated after the Androscoggin River flooded its banks in 2003, causing about $2 million in damage to scores of homes, businesses and buildings along routes 140 and 108 in the town center.

Since then, the fire station and town office have been relocated, dozens of ruined homes have been bought and demolished, and 30 acres on Edmunds Road has been purchased and cleared to build new homes, all with $5 million from state and federal governments.

Lazarus Project

The relocation effort, coordinated by Diane Ray, was called The Lazarus Project, and the new housing site was called Village Ridge. The total price tag was expected to be between $6 million and $7 million, she said.

Financing the project was approved in 2004 and later rescinded three times in special town meeting votes, but Ray said the project itself was never voted down.

The work done at Village Ridge was dependent on getting the funding, she said, and since voters turned down the money, the town is liable for the $177,535 already spent.

Two weeks ago

In July, selectmen voted 3-2 not to hold any more hearings on Village Ridge, but two weeks ago resident Sue Gammon presented them with a petition asking the town to:

• Cease all efforts to sell the Village Ridge property on Edmunds Road;

• Hold at least three public hearings on new information on the project; and

• Hold a special town meeting to accept a $336,000 sewer grant, a $448,000 sewer loan, a $355,000 water grant and a $434,000 water loan, all from USDA Rural Development.

With the eventual approval of that petition, Gammon offered the agendas for each hearing on Thursday night:

• Monday, Sept. 8: Discuss the water district and the impact of the buyout on water and sewer and what lies in the future. Rural Development representative Bobbi Arnold will explain the loan/grant package.

• Monday, Sept. 15: Walk the village site, weather permitting. Wright Pierce will present Engineering studies and Greater Brunswick Housing Corp. will discuss affordable housing with designs and plans.

• Monday, Sept. 22: Discuss the impact on taxes.

On Sept. 23 from 10 a.m. to 8 p.m. voters will decide whether to accept four grants for the village project.

The town owes $37,035 for work done on the project before the town voted down all funding. The board voted Thursday night to pay three of the smaller bills.

Ray told the board Thursday, “If the village (project) passes in the referendum, all debts will be covered with grants. If not, the town will have to vote to sell the land to pay the debts,” which total more than $177,000.

Selectman Lisa Cummings gave an emotional plea to townspeople attending the meeting.

“It’s disgusting how people are being treated in the stores. Diane has been verbally abused, and I have been targeted as a selectman.

“It’s very upsetting,” she said. “Yes, we are not all perfect, but this finger-pointing has got to stop. We are grown people, not teenagers. Stop the gossip. If you have problems, bring them to us, not to the town through gossip.”

Comments are no longer available on this story