AUBURN – Work replacing natural gas lines along Court Street will move to the side streets next week.

But Gary Johnson, Auburn’s assistant city engineer, said the Northern Utilities project won’t cause as many delays next week.

“They don’t have to do the trenching work on the side streets,” he said. “Most of the work next week will be lining the existing pipes with plastic, and they don’t need to dig up the entire street to do that.”

The company is being required to replace all cast-iron gas mains in Lewiston and Auburn as part of a settlement with the state Public Utilities Commission. That came after a January 2004 explosion on Main Street in Lewiston that was blamed on a leaking Northern Utilities gas line. The explosion leveled the old Hotel Holly and the Lewiston Radiator Works, and injured five people.

Crews are replacing about 29 miles of natural gas pipe in Auburn alone over three years. When the work is finished, crews will have replaced almost 57 miles of gas mains in both cities.

This phase of work includes digging on Court Street between Goff and Haskell streets.

Crews will work their way west along Court Street next week, doing work first on Forest and Fairmont avenues before crossing to the northern side and doing work on Holly, Granite, Josslyn and Fern streets and Dexter Avenue. Crews will move back to the south side afterward, doing work along Russell and Dana avenues, Summit, Merrill and Hazel streets, and Cushman Place.

Another Northern Utilities crew will begin working in New Auburn next week, along Cook Street between South Main and 8th Avenue.

Johnson said he expected the natural gas line replacement work along Court Street to continue for the next month, before joining the other crew in the New Auburn area. They should continue working in New Auburn through the summer, Johnson said.