Pull-out:
New town office/police station cost
Building purchase: $270,000
Architectural fees: $35,000
Zachau Construction bid: $540,720.
Second-hand generator: $9,000
Contingency: $14,076.96
Paving parking area: $50,000
Total cost: $918,796.96
Source: Jay Town Manager Ruth Marden
$177,500 more requested for municipal building
JAY – The new town office/police station will cost $918,796, Town Manager Ruth Marden said Tuesday. That includes money for a backup generator, paving and contingencies.
Voters will be asked to transfer $177,500 from a $5.5 million undesignated fund to the building reserve account to complete work on the former Jay Family Restaurant on Route 4.
The special town meeting will be held at 7 p.m. Tuesday, Dec. 4, at the Jay Middle School cafeteria, a half hour after selectmen meet.
Selectmen’s Chairman Bill Harlow has said he will motion to have a secret ballot for voters to decide the money transfer article.
More than five years ago a building committee determined a new municipal complex would cost between $1.2 million and $1.75 million. Taxpayers tucked away $100,000 each year for it.
A feasibility study showed it was more cost efficient to buy a new building than renovate the current one.
Resident Janet Diaz offered to sell the former restaurant to the town for $250,000, and voters approved it last January, adding $20,000 for gutting it. They also voted to spend $459,000 to retrofit it.
“At the time we purchased the building and the town voted to buy it, we were under the assumption that it would be close but that we would be able to recondition the building for what we had,” Marden said. “However, when the actual bids came in, it was apparent that we could not. We have scaled back the renovations as far as we can and now we are going to have to rely on the public’s good judgment to transfer the funds to finish this project. No one has tried to pull the wool over anyone’s eyes.”
Zachau Construction of Freeport had the lowest bid of 10: $540,720.
Additional costs are $9,000 for a rebuilt or second-hand generator, $50,000 for a pavement on the parking area and $14,076.95 for contingencies.
“We need a generator,” she said. “(Monday) I asked the chief to investigate the possibility of getting grant funds from (the federal Department of) Homeland Security. We have no idea if that is going to happen or not, but we’re leaving no stone unturned, and I also contacted state surplus and they are looking for a generator for us. So we’re really trying to hold costs down.”
The existing municipal building relies on a sewer pump station generator across the street from the office.
Money from the sale of town office building, which is assessed at $130,000, and more than $100,000 extra in state revenue than had been anticipated are expected to repay the undesignated fund account.