2 min read

BANGOR (AP) – A new round of changes to Plum Creek Timber Co.’s proposed development of hundreds of house lots and two large resorts in the Moosehead Lake region will delay public hearings on the project, which were to begin next month.
Plum Creek unveiled its latest revisions Wednesday, the same day the Land Use Regulation Commission voted in Orono to delay public hearings, which were to begin Nov. 3 and continue with a series of work sessions. The schedule was to wind up with a final meeting on Nov. 18.
The commission now plans to set a new hearing schedule on Nov. 7.
The wilderness zoning agency decided to drop its previous schedule when the Seattle-based developer offered more alterations to the third version of its development plan. The modifications are in response to written criticism submitted in late August by several state and federal agencies.
Plum Creek is asking LURC to rezone land for 975 house lots and two large resorts near Moosehead Lake. Plum Creek has also offered to conserve more than 400,000 acres of forest land in the region.
The changes in Plum Creek’s plan include setting aside land for future recreational needs, providing road easements to ensure public access and taking more steps to eliminate additional development in residential and commercial zones.
The developer’s latest changes call for permanent caps on development within the proposed subdivisions, state-held road easements granting public access to 57 miles of roads within protected lands and interest-free loans to build a peak-to-peak hiking trail in the region.
The changes also propose the creation of a “community stewardship fund” funded in part by 2 percent of the sale price of residential lots.
Luke Muzzy, senior land asset manager with Plum Creek, said he was disappointed the hearing schedule has been pushed back but said each revision, based on public concerns, has improved the plan.
Some LURC commissioners expressed frustration with the delay.
“The public perception, and I guess I’m part of the public here, is this has been a moving target from Day One,” said Stephen Wight, LURC’s co-chairman. “We are on the third application and this third application is being modified until who knows when.”

Comments are no longer available on this story