DIXFIELD – Christmas came before Thanksgiving for SAD 21 and Superintendent Thomas Ward.
On Tuesday afternoon, Ward, state and architectural officials opened three construction bids for the district’s new $14 million, 380-pupil elementary school. Pending state approval of the lowest base bid – $9.88 million by Langford and Low Inc. of Portland – groundbreaking could begin within the next four weeks, Ward said.
“It was a very nice Christmas present. We’re very excited,” he said after the meeting, which was held in his office building’s conference room off Weld Street.
The other two bids were $10,757,000 by J.C.N. Construction Co. Inc. of Manchester, N.H., and $10,363,000 by Davis and Hanscom Inc. of Steep Falls. Langford and Low’s bid was the last one opened.
“I was happy with the other two, but you couldn’t have asked for a better bid” than Langford and Low’s, Ward said.
A fourth company, P. J. Stella Construction Corp. of Wakefield, Mass., which, like the other three, were pre-approved by the state to bid on the project, failed to show for Tuesday’s meeting.
Also, pending state approval, site work excavation will be done by K and K Excavation Inc. of Turner, which had the lowest sub bid at $2,499,991.
“Considering the price of fuel, we were very nervous about the bids. But, I think, (project) delays and the drop in fuel prices really had an impact on the bids. The contractors weren’t quite so nervous,” Ward said.
The project was delayed late last year and again this past fall. Last December, despite a warm wet winter, the 35-acre site in Peru off Route 108 froze, postponing a state-required American Indian archaeological survey to this past spring. Because no artifacts were found, the district could finally buy the land, which it did in September.
Then, this autumn, the district had to resolve vernal pool permitting issues with the U.S. Environmental Protection Agency, Maine Department of Environmental Protection, and U.S. Army Corps of Engineers.
Ward said the essential breeding habitat pool is on the other side of a planned legal-size athletic field closest to where the new school building will be built.
A compromise was worked out to protect the vernal pool by moving planned athletic fields and a septic drainage field out of a 250-foot radius zone of it.
In addition to the base or general construction bid, Langford and Low also made the lowest bid – $1,302,945 – on alternate work, which includes, upgrading porcelain tile, installing photovoltaic and solar hot water systems, equipment for food service, appliances, bleachers, air conditioning for the administration area and library, and site improvements.
“We were very fortunate on that. Usually, on a project like this, if you get some in, that’s good, but, we were able to get them all in. That’s exceptional. So, as long as this holds true, we’re in very good shape,” Ward said.
The state will pay the lion’s share of the $14,012,035 total project cost.
Barring any unforeseen complications, Ward said new school construction could be completed by July 2008, with kindergarten-through-fifth-grade students currently attending Dixfield and Peru Elementary schools able to move in that fall. The new school will also offer a new-to-the-district prekindergarten class.