State fire marshal tells Rumford to make the Municipal Building comply with safety laws
RUMFORD – Residents can expect to see a question on the Nov. 7 ballot asking for approval to make repairs and modifications to the Municipal Building so the town can continue using it. The cost of the work is estimated to be at least $800,000.
“You have a letter of deficiency and you have to submit a plan of correction. We will work with you, but you don’t have an endless date,” said State Fire Marshal John Dean at a special meeting of several selectmen, Building Committee members and a representative from Maine Historic Preservation Thursday afternoon. “A finite date would come from a vote this year.”
“This isn’t an open-ended time frame. We will take action,” he added.
Nelson Collins, Office of the State Fire Marshal’s supervisor of licensing and inspections, said the building would be closed if the town does not make it safe for use.
A letter he wrote earlier this month to town officials calls for a plan of correction submitted by Dec. 11 that shows the time frame for meeting the minimum life safety requirements.
That means, said Town Manager Steve Eldridge following the 90-minute meeting, that a vote will be held in November to approve seeking funds for the work, then another vote will be taken in June to accept funds to do the necessary work.
“We would expect an update on Dec. 11,” Dean said.
Eldridge said the town will begin the process of going through the state bond bank or some other funding avenue soon. The state offers loans for such projects twice a year – in the fall and in the spring. He said a meeting of the Building Committee will be called the week of Oct. 9 to work out details of work and estimated costs of what must be done.
Collins said that a maximum of 49 people can be present in the Municipal Auditorium until additional and modified exits are in place.
Rumford fire Chief John Woulfe, who has been involved in the Municipal Building and fire station life safety issues for several months, agreed that a 49-person maximum was necessary.
Collins said, too, that if the building continues to be used if it is directed to be closed, the town could be summoned and subject to a $10,000 fine, and individuals up to $1,000.
Among the minimum modifications that must be made are approved exits from the auditorium and courtroom, restructuring an exit at the back of the auditorium, handicapped accessibility into the building and at sites inside the building, installation of a fire alarm system and other safety matters.
Eldridge said a preliminary estimate, which he termed bare bones, called for at least $800,000. That figure would not bring any of the similar issues in compliance at the adjacent fire station.
Although life safety issues are paramount, Dean said his office has worked with Maine Historic Preservation when he’s dealt with buildings listed on the National Register of Historic Places, as the Municipal Building is.
“This is a beautiful building, but I’m not in favor of substituting a historic plaque for a gravestone,” he said. “These buildings were built at a different time in history. It’s sometimes a challenge to provide life/safety and historic preservation.”
Michael Johnson, representing Maine Historic Preservation, said it is possible to integrate safety issues without destroying the historic character of a building. His agency, along with the town’s architect, would likely work together to meet fire marshal requirements.
Comments are no longer available on this story