KINGFIELD – Residents will finally get a chance to offer comments about a proposed Poland Spring bottling plant during a public hearing slated to start next week.
The plan for the controversial plant has been in the works for more than two years and has been a source of concern for both residents and Poland Spring Water Co. officials. Some residents oppose the plant, but the majority of voters are for it, as shown in Poland Spring’s landslide victory during a moratorium vote this spring. Residents voted against a moratorium on industrial building by a margin of 3-to-1.
First pegged at more than $100 million, the plant’s expected cost has been reduced to $60 million to $80 million in recent months, in part as a response to residents’ concerns, Poland Spring Natural Resources Manager Tom Brennan said earlier this summer. Resin forms for the plastic bottles will not be made at the plant, Brennan said, because making them and subsequently storing them is the noisiest thing that goes on at Poland Spring’s plants.
Next week’s public hearing marks the beginning to an end of a long process for the town. After townspeople and company representatives have a chance to speak at the hearing, the board will set to work evaluating the proposal, Planning Board Chairman David Guernsey said. Sometime after the hearings, the board will vote on whether to grant the company the permits it needs to build the plant.
Either way, the days of speculation as to what’s going to happen are almost over. Guernsey said Wednesday and Thursday he expects a crowd at the hearings. “I’d say there’ll be 50 and up,” he said. “This is the formal public hearing where the people will hear first hand (about the project).”
Thursday from 7 to 8 p.m., the Planning Board has scheduled a time for public comment. Anyone who wants to speak or ask questions about the project can do that then, Guernsey said.
Prior to the midweek hearings, a variety of planning meetings are scheduled to take place Monday, Sept. 11.
Some members of the Planning Board will hold a planning meeting at 4 p.m. Monday. They have requested people who have information to present at the hearing will come to Monday’s meeting. “It’s just to find out who the major presenters are and try to schedule (the presentations),” he said.
At 6 p.m., the Water District plans to meet to consider taking final action on an agreement between the district and Poland Spring.
The bottling company asked the district this spring to enter into an agreement with them, whereby the district will build a pipeline between the proposed plant site and a water source in town, and let Poland Spring pay a fee to use it.
Poland Spring officials had originally hoped to build and own the pipeline but were thwarted this spring when the state Department of Transportation ruled the private company cannot legally run the pipe on Route 142, a public right of way.
Members of the water district met this week in executive session and tentatively decided to sign an agreement with the district, District Chairman Bob Barnes said Thursday. On Monday, the board plans review and possibly sign it, he said. Under the agreement, Poland Spring will pay the district $20,000 per year to use the pipe. The company will also pay the water district’s $5,000 consultant fee, donate $250,000 toward an infrastructure upgrade, and donate $120,000 toward a new well, Guernsey said.
“We feel this is fair to the district,” he said. We have said we’re going to deliver that water – well, we have to make sure we can do it!”
The agreement is the last piece of the application the Planning Board needs to grant Poland Spring a building permit – if the board decides the rest of the application is in order. “I fully expect that whatever the Water District and Poland Spring come up with would be sufficient for us to conclude the process,” Guernsey said.