MONTPELIER, Vt. (AP) – The Public Service Board on Friday conditionally approved a major new power transmission project proposed to serve fast-growing northwestern Vermont.
“The board found that increased electrical demand in northwestern Vermont, in conjunction with the lack of major improvements to Vermont’s transmission system for many years, has resulted in lower than desirable levels of reliability for that region,” the three-member panel said in a statement accompanying its 240-page order.
The board approved the project with what it termed substantial conditions. Among them were the use of non-reflective wires throughout, burying 1.4 miles of the line underground near the Lake Champlain shoreline in Shelburne, and moving a major substation planned for New Haven.
Velco spokesman David Mace said the company hoped to have a 345-kilovolt line between West Rutland and New Haven completed by the summer of 2006 and the entire project, including a new 115-kilovolt line between New Haven and South Burlington, completed by the end of 2007.
John Donleavy, Velco’s president and chief executive officer, said in a brief interview, “We are very pleased with the ruling by the Public Service Board that this project is necessary and promotes the general good of Vermont.”
Under the rules of the regional power dispatch agency ISO New England, Vermont ratepayers will bear only about $12 million of the project’s $129 million price tag, but also will chip in for transmission projects elsewhere in the region.
Project opponents vowed to continue their efforts to block it.
“You can count on a legislative response,” said Sen. Vincent Illuzzi, R-Essex-Orleans, chairman of the Senate Economic Development Committee.
“I consider this decision round one. There are several more rounds to go before the bell rings and construction starts.”
James Dumont, a lawyer for the town of New Haven, which has fought a major expansion of the Velco substation there, said he expected opponents would also contest wetlands permits the project must get from the state and the U.S. Army Corps of Engineers. He said the company also should expect big fights from individual landowners as it tries to acquire additional right of way by eminent domain.
Northwestern Vermont has been identified by ISO New England as one of three transmission bottlenecks in the region. The others are greater Boston and southwestern Connecticut.
Velco officials have argued from the inception of the project, first taken to the board 18 months ago, that the high demand, coupled with a lack of high-voltage transmission lines or nearby power plants serving northwestern Vermont, placed the region at unacceptably high risk of blackouts during peak demand.
And peak demand is growing: Vermont set an all-time record of 1,086 megawatts of simultaneous demand on Dec. 20.
Critics of the Northwest Reliability Project – or NRP – sought to persuade the board and the public that Velco had not done enough to study alternatives to the power lines, including energy efficiency and small-scale, local generation.
The critics also voiced concerns about studies showing exposure to the electromagnetic fields put off by high-voltage power lines as a possible cause of cancer. In addition, they said some of Vermont’s most valuable real estate – especially in the Lake Champlain shore towns of Shelburne and Charlotte – would be marred by the taller poles the new lines would require.
The board said small-scale local generation would not be enough to remove the need for the transmission upgrade. Rather, the local generation option would require “building and fueling at least three mid-size 40 (megawatt) bulk generation power plants in Chittenden County.”
It also said a “major reduction in expected demand,” achieved through efforts at energy efficiency unprecedented in Vermont, would be required to offset the need for the power lines.
On the health issue, the board cited a report from the National Institute of Environmental Health Sciences saying that the scientific evidence on any threat from electromagnetic fields was weak. It said the best course was “prudent avoidance” of people coming in close contract with the lines, saying it would support “policies that limit magnetic field exposure whenever this can be done for a small investment in money and effort.”
The board faulted Velco for “deficiencies in forecasting expected electricity demand … leading to a need to consider and install new facilities in a shorter time-frame than desireable.”
It also faulted Velco for not giving early enough consideration to alternatives like energy efficiency, “leading to the present situation in which transmission construction must be chosen as the least-cost reliability solution, despite the fact that an earlier, greater, effort at efficiency might have opened up alternatives.” “
AP-ES-01-28-05 1634EST