PublishedOctober 13, 2022
Storm bringing heavy rain and winds expected to stay around for most of Friday
The storm has the potential to produce flooding and scattered power outages.
-
PublishedOctober 3, 2022
Maine DEP wants sections of proposed NECEC corridor cleaned up
The project to build a power transmission line through western Maine is suspended, but the state said the contractor must clean up crane mats and previously cut trees.
-
PublishedSeptember 27, 2022
Judge schedules April trial in electricity corridor case
The latest phase of a lawsuit will determine whether the builders of the 145-mile transmission line had done enough work to have 'vested rights' in the project, which would nullify a state referendum vote to block it.
-
PublishedSeptember 24, 2022
Winds from Fiona cause power outages in Maine
Much of the outages were in Somerset County, with 1,009 customers in the dark at one point.
-
PublishedSeptember 18, 2022
Effects of climate change underlie CMP rate hike request
Everyone wants a stronger grid. But can beleaguered customers afford it now?
-
PublishedAugust 30, 2022
Maine Supreme Judicial Court sends CMP corridor case back to lower court
The state's high court ruled Tuesday that a referendum blocking the transmission line would be unconstitutional if a lower court determines the project was already too far along at the time of the vote.
-
PublishedAugust 29, 2022
Dump truck hits utility pole in Waterville; 2,600 lose power
Truck was on Eustis Parkway Monday, assisting with replacing a water main when it struck the pole, according to officials.
-
PublishedAugust 11, 2022
State officials to oppose Central Maine Power rate hike
The Governor's Energy Office filed Thursday for intervenor status to oppose the increase, which would add about $10 a month to an average customer's bill.
-
PublishedJuly 21, 2022
State environmental board lets permit stand for transmission line project
But the energy corridor's fate still hinges on a Maine Supreme Court ruling on the validity of a 2021 referendum that was designed to kill the $1 billion construction project.
-
PublishedJuly 6, 2022
Maine sees the future of power transmission, and it won’t always include big new lines
Big batteries and efficiency are chosen as an alternative to a new Brunswick-Topsham power line, thanks to a new law that pushes utilities to explore new ways to assure reliability.
- ← Previous Page
- 1
- …
- 4
- 5
- 6
- 7
- 8
- …
- 40