PublishedApril 20, 2023
Work can resume on CMP power-line project, jury rules
Construction of the 145-mile line through western Maine has been stalled since a 2021 voter referendum that opposed the $1 billion project.
-
PublishedApril 11, 2023
Power line construction moved ahead on good-faith schedule, jurors told
New England Clean Energy Connect, backed by Central Maine Power and its affiliates, was repeatedly forced to change timeframes, lawyers for the project said on the second day of a civil trial.
-
PublishedMarch 26, 2023
War over CMP corridor enters new phase – a jury trial
A lawsuit involving more than 2 million pages of evidence will confront jurors, who must decide whether Central Maine Power's parent has vested rights in the project Mainers voted to kill in 2021.
-
PublishedMarch 26, 2023
The CMP corridor battle: Where does the money come from?
The fight over the proposed New England Clean Energy Connect hydropower transmission line has become a multimillion-dollar industry of its own.
-
PublishedMarch 21, 2023
CMP warns customers to be careful after wave of scam calls
Scam callers have been trying to dupe electricity customers in Maine and elsewhere by threatening to turn off their service.
-
PublishedFebruary 2, 2023
Federal regulators clear connection obstacle in fight over CMP corridor project
The Federal Energy Regulatory Commission ruled Wednesday that equipment must be upgraded at a New Hampshire power plant so the transmission line can connect to the regional grid.
-
PublishedDecember 29, 2022
Opponents of consumer-owned power effort submit signatures for competing ballot question
The parent company of Central Maine Power, Avangrid Inc., is fighting against an initiative to create a consumer-owned utility in the state.
-
PublishedOctober 3, 2022
Maine DEP wants sections of proposed NECEC corridor cleaned up
The project to build a power transmission line through western Maine is suspended, but the state said the contractor must clean up crane mats and previously cut trees.
-
PublishedSeptember 27, 2022
Judge schedules April trial in electricity corridor case
The latest phase of a lawsuit will determine whether the builders of the 145-mile transmission line had done enough work to have 'vested rights' in the project, which would nullify a state referendum vote to block it.