LIVERMORE FALLS — Middle school Principal Robert Kahler gave RSU 36 directors a tour of the 45,138-square-foot building Wednesday prior to the school board meeting.

The board is faced with making a decision on whether to close the school and send the students to Jay or keep it open.

The original building was built in 1916 and was 19,500 square feet. A 14,406-square-foot gym was added in 1953 and an 11,232-square-foot addition where the cafeteria and serving kitchen are located was built in 1982, according to McCormick Facilities Management that did a facilities analysis on both RSU 36 and Jay schools in 2008.

There three small classrooms (300 to 600 square feet), 11 standard classrooms (600 to 800 square feet), and three large classrooms (800-plus square feet usually used for labs), the study states. Not included in those numbers are the spaces affiliated with music classes or the gym.

The current replacement value is $4.6 million. McCormick’s study made the observations that combining the requirements and deferred renewals, the cost to return the facility to an acceptable condition for educational use is a total of $3.1 million, which represents 77 percent of its current replacement value.

Among the observations made by directors and school officials Wednesday were the 14-foot ceilings, bathrooms that did not meet Americans with Disabilities Act requirements, open stairwells, wooden railings for staircases, and that it did not meet current codes.

Advertisement

According to McCormick’s study, getting the building to comply with current codes and standards would total $328,327.

Directors checked out the boiler room, classrooms, cafeteria, band room, and most every room on every floor.

Board Chairman Ashley O’Brien said that the building has a 16,000-gallon tank to hold No. 2 fuel oil. He also said under the gym there is a 1,000 gallon water storage tank that is heated and used for showers and the kitchen, mostly.

“We don’t use anywhere near that amount,” O’Brien said.

The space under the gym is accessed through the boys’ locker room and there is no heat in the space, custodian Paul “Tiny” Burkey said.

There are three shower stalls in each of the girls’ and boys’ locker rooms that are in what Pratt referred to as the “dungeon.” They are separated from the academic wing by a long hallway.

Advertisement

The critical requirements in McCormick’s study total $15,390. The major deficiencies identified are non-fire-rated stage curtains and eaves ventilation. It was unclear whether those deficiencies were fixed after the 2008 study.

There are requirements identified as potentially critical totaling $201,773. The major deficiencies identified involved the electrical system. Some electrical work has been done since the study was conducted.

There are requirements identified as necessary but not yet critical totaling $239,675 with the major issue involving Americans with Disabilities Act accessibility.