OXFORD — A misunderstanding of process orders and not Department of Homeland Security issues may be the cause for a more than two-month delay in the arrival of the Oxford Hills School District’s biomass furnace from Austria, school officials said Wednesday.

“The story changes,” Project Manager John Parsons said following a meeting with Siemens Technology officials, hired by the school district last year to oversee the biomass furnace project at Oxford Hills Comprehensive High School.

Siemens hired the Viessmann Group of Austria, a leading manufacturer of heating and renewable heating systems, to build the school’s biomass furnace.

“The Maine representatives of Viessmann are in Europe trying to get some answers,” Parsons said. “It appears the problem has been a backlog of orders in Austria.”

Siemens initially believed Homeland Security issues, such as container requirements, would delay the project, Parsons said.

The latest reasoning behind the delay of the arrival of the furnace from Jan. 6, when it was expected to be fired up, to mid-March, could not be confirmed until next week, when representatives arrive from Europe with more information. Parsons said it appeared to be a misunderstanding of how the process orders work.

Advertisement

He said school officials were told it would take about 26 weeks from the time the order was placed (in late spring) to receive the furnace, which must be shipped from Austria, where it was built. “It may be different for Viessmann,” he said of when the manufacturer decides it can deliver an item.

Parsons said that in addition to the container issue, Siemens expressed concern about a delay in shipping the furnace because of increased security concerns.

“The other factor was the anticipated increase in scrutiny of cargo coming into the country,” Parsons said, especially after the recent discovery of a shipment of explosive materials from Yemen aboard cargo and passenger planes.

The proposed $2 million-plus conversion project from oil to wood chips at Oxford Hills Comprehensive High School was planned to address escalating fuel costs and to make the district more energy independent by reducing dependence on foreign oil sources.

The new furnace is expected to save the district as much as $120,000 a year in annual fuel savings and to supplement about 90 percent of the consumption of No. 2 fuel oil used to heat the high school.