HARRISON — Townspeople in Harrison and Otisfield may be given a deadline to decide whether to fix or close the bridge at Scribner’s Mill following an inspection by the Maine Department of Transportation this year.
Town Manager Bradley Plante of Harrison said he spoke with MDOT bridge management engineer James Foster and was told that the inspection would take place this summer or fall. MDOT inspects bridges every two years, and is bumping up a 2011 inspection scheduled for the Scribner’s Mill bridge. The last inspection of the span was in July 2009, according to MDOT records.
Problems with the bridge include cement breaking away on some abutments and supports that need to be re-welded, Plante said. The bridge has a posted weight limit of 6 tons, but Plante said people have reported overweight vehicles using it.
The bridge, which was built in 1936, crosses the Crooked River and links Scribner’s Mill Road in Harrison and Jesse Mill Road in Otisfield. It consists of an open-grate steel deck atop concrete-capped stone abutments. The MDOT’s latest report rated the substructure in “serious” condition and the superstructure and deck in fair condition.
Bancroft Construction estimated that repairing the bridge would cost just under $100,000. Selectmen in both towns are waiting on the state’s new findings, and Plante said the MDOT might require certain repairs to be completed before a certain date.
Approval of funds to repair the bridge would hinge on approval at public meetings in both towns. The towns are responsible for deciding whether the bridge will be closed, but MDOT can immediately close a bridge in the event of an emergency or “imminent hazard” to the public, according to its website.
Plante said a traffic count conducted in May determined that about 70 vehicles cross the bridge each day.
“It’s a very low-used bridge,” he said.