AUBURN – Four state road projects in Auburn and one in Greene will go to Pike Industries this summer.

Pike bid $971,000 on the road overlay projects, said Maine Department of Transportation’s Bill Bourne. Work is set to begin during the first week in April and wrap up by July 31.

Crews will mill and grind the existing pavement off of the roads and replace them with a new layer of hot asphalt. They’ll also repair and upgrade crosswalks and curbs along the way.

Work is scheduled for the following streets:

• In Auburn, Court Street from South Goff Street to Russell Avenue;

• Spring Street from Court to Elm streets;

• Goff Street from Court to Dennison streets;

• Mount Auburn Avenue from Turner Street west to about Gracelawn Road;

• In Greene, Route 202 north from the Lewiston city line about three miles.

Bourne said he didn’t know which project would begin first.

“That’s another thing we expect to get settled with the contractor in the next couple of weeks,” he said.