State’s road work will snarl traffic on Route 202 Wednesday.

Crews should move their sidewalk building work from Turner Street to Center Street later this week.

Work on a new sidewalk along Turner Street near Wal-Mart should be substantially complete by Wednesday and open for pedestrian traffic. That means crews doing that work should be able to pick up and move to Center Street. They’ll close one northbound lane of Center Street south of the Vietnam Veterans Bridge overpass by Wednesday.

“That’s going to be a little more involved work,” said pavement technician Paul Niehoff. Crews need to build small retaining walls in two places where the new sidewalk will cross in front of the Pizza Hut.

“So, we should spend about a month on that project,” he said.

Elsewhere in Auburn, crews will be putting down finishing coats of asphalt on several streets west of Western Avenue and south of Court Street. Crews built a new storm sewer line there last year, and the paving is the last part of that work. Dana, Carol and Hillside avenues, and Goodrich, Merrill and Barton streets will all be paved beginning Monday.

City crews replacing drains on Stephens Mill Road should wrap up that work this week, as well. They should begin reclaiming that road – grinding down old pavement and replacing it – in the next several weeks.

City crews might also begin paving Moosebrook Road later this week, Niehoff said.

“That depends on our contractor and how the weather holds up,” he said.

State crews will be moving, as well. Work repaving Mount Auburn Avenue east of Wal-Mart should wrap up by Wednesday, according to Project Manager Bill Bourne. Then crews will move to Route 202 and begin paving that road, from the Lewiston city limits north to Allen Pond Road. Flaggers will be closing lanes of that road for the next week, he said.

“So if they can plan ahead, people coming in from Greene may want to avoid that altogether and take College Street,” Bourne said.

State highway department curb work on Court Street should ease up as well, he said.

In Lewiston, crews will be concentrating on storm sewer separation work on Pine and Bartlett street. Pine Street will be closed on and off for the next two weeks, according to Public Works Director Dave Jones. Bartlett Street will be down to one lane, he said.

Some lanes near the intersection of Main and Lincoln streets will be closed this week, as crews continue working on Gateway Park there.

Lewiston water crews will be closing Horton Street to local traffic only and shutting down Sabattus Street as well while they replace a water line.

Jones said five streets are ready for paving work but that work won’t begin until later in May. Crowley, Dyer and Deer roads, and Pine and Webster streets are all scheduled to get a new surface layer of asphalt, possibly after May 24.