2 min read

auburn – The traffic improvements planned for the Mount Auburn Avenue/Turner Street area will likely cost between $4 million and $5 million. The city is prepared to act as banker for the project, providing upfront money through a bond. That money would be repaid through a tax increment financing plan and impact fees assessed on future developments as they come onto the tax rolls.

Developer George Schott paid $150,000 to fund the traffic study on which the improvements are based. Under the TIF plan, he could be credited up to $1.75 million over a 15-year period to recover the costs he paid upfront to develop the properties such as Kohl’s and Mount Auburn Plaza.

So if, for example, a new store locates in the designated area and generates $1 million in property taxes, a percent of that would be credited to Schott under the TIF through a tiered system – the more development he attracts, the faster he recoups his costs. If he brings in between $5 million and $11 million, he gets 30 percent – or $33,333 in the example above – credited. For development between $11 million and $15 million it’s 35 percent and above $15 million, 40 percent.

The remaining $66,666 of that store’s tax bill would go into a fund to pay off the city’s bond for the traffic upgrades until the debt is retired.

The intersection doesn’t need other changes to its infrastructure to sustain the 450,000 square feet of new development expected, said Roland Miller, city economic development chief.

That area has been earmarked for retail development in city plans dating all the way back to the 1960s. There is sufficient access to water, sewer and power lines to support the additional development, he said.

– Carol Coultas

Comments are no longer available on this story