NEW GLOUCESTER – A decision on a contractor to build a fire station remains mired in the bidding process.
The Fire Station Committee ranked the $2.4 million proposal from Smith Reuter Lull Architects of Lewiston, Taylor Engineering Associates of Auburn, H.E. Callahan Construction Co. of Auburn and Bennett Engineering of Freeport the highest.
It was the second lowest bid of four.
The committee ranked the $1.7 million proposal from Bunker and Savage of Augusta and Zachau Construction of Freeport the lowest because it lacked items listed in the bid specifications. It was the lowest priced offer.
After being directed by selectmen to negotiate with Bunker and Savage, and Zachau Construction to bring its bid up to specs and the $2 million cap for the project, members said they were uncomfortable not giving other bidders the same opportunity to meet the cap.
Selectman Steven Libby made a motion to award the contract to Savage and Bunker, and Zachau Construction, after clarifying the missing items, and capping the project at $2 million. He and Lenora Conger voted for it, and Chairman David Lunt was opposed.
“I have been very uncomfortable going out to one of the four bidders. This is a problem for me with the direction we are going,” Lunt said.
Town Manager Rosemary Kulow agreed, saying the same opportunity needs to be offered to the others.
On Tuesday, the committee reviewed a new $2 million proposal from Savage and Bunker, and Zachau Construction and concluded it still does not meet bid specs.
Fire Chief Gary Sacco, who chairs the committee, said voters will ultimately decide whether to build the station on 25 acres beside Route 100 near Pine Tree Seeds.