LEWISTON – Road crews should put the finishing touches on new Main Street pavement between Blake and Bates streets Tuesday.
The work completes an emergency clogged sewer line replacement project that began in February.
Crews began digging the 170-foot-long trench in the middle of Main Street on Monday morning, part of the work to get ready for final paving.
The work is scheduled to continue Tuesday morning and wrap up by late afternoon. The city will keep at least one lane open in either direction, but parking along Main Street won’t be allowed.
Crews discovered the clogged sewer line in January, identifying it as a white blob blocking about 50 feet of pipe. They tried to unclog the pipe for seven days using high pressure water and metal augers and rods.
Road crews began digging up the road and discovered that the line had collapsed and was surrounded by dirt-free voids, areas where the soil meant to support the pipe had washed away. The old pipe was 12-inch, unreinforced concrete.
Crews finished replacing the pipe in February, leaving the final paving until now.