PERU – Prior to Monday night’s SAD 21 board meeting, a Portland architect brought directors up-to-date on the 300-pupil elementary school project.
Lyndon Keck of Portland Design Team Architects said he expects construction to start by Nov. 20, barring any complications.
“It’s better than what we had anticipated,” Superintendent Thomas Ward said after the meeting.
On Sept. 7, the district closed on 35 acres in Peru off Route 108 that were offered for $55,000. The state will pay about half that, SAD 21 the rest.
Final comments from the Maine Department of Environmental Protection on the project were completed last Thursday.
Keck said that because the district didn’t receive enough bids from contractors the last time advertisements were run, another round of ads were sent out Monday and more set for Thursday, Sept. 21.
A meeting with the Maine Board of Education’s subcommittee is scheduled for Oct. 2, followed by a vote on funding approval Oct. 11.
Bidding starts Oct. 12 with pre-qualifying done six days prior.
Keck said he also expects DEP approval by Oct. 12.
Bids are due by Nov. 9 and will be reviewed by SAD 21 directors at their regular meeting on Nov. 13. Directors at Monday’s meeting after Keck’s presentation agreed to change their meeting dates from the third Monday of each month to the second, after October’s meeting. Additionally, the time has been changed from 6 to 6:30 p.m.
Keck sought and received board approval to put the project out to bid again.