OXFORD – Upgrades to the runway at Oxford County Regional Airport will be put on hold until spring after a contractor told the county he could not do the work for the price he quoted.

County administrator Carole Fulton said Gendron and Gendron of Lewiston would take a $132,000 loss if they completed the work at their bid price of $1,281,063. A letter from the company cites the prices and availability of asphalt as contributing to the problem.

Fulton said the project will be put out to bid again in the interests of fairness to other companies. Shaw Brothers Construction of Gorham bid $1,553,850 for the project, while K & K Excavation of Turner bid $1,820,698.

The plan for the airport includes rehabilitating the 3,000-foot runway, replacement of runway and taxiway lights, tree-clearing, sign replacement and earthwork. Construction was scheduled to begin after Labor Day and close the airport for 21 days.

The airport was the recipient of a $1,873,400 grant from the Federal Aviation Administration to be put toward the project.