EUSTIS – Drivers using Route 27 between Eustis and Chain of Ponds, just south of the Canadian border at Coburn Gore, should expect to encounter construction for the remainder of this construction season and most of next, according to the Maine Department of Transportation.
Clearing and excavating operations began July 5 signaling the start of work on approximately 15 miles of highway improvements in that section of the Route 27 corridor.
The project begins on Route 27 about three miles north of the junction of Routes 16 and 27 in Stratton Village and extends north to the south end of an earlier improvement project at Ledge Hill in Chain of Ponds.
The clearing and excavation will include some locations where ledge will have to be blasted so it can be removed.
“In a few of those areas, because of the location of the ledge, the blasting wil cause the existing roadway to be buried by the blasting debris. The contractor will have several pieces of large equipment standing by to clear the roadway as quickly as possible after each blast, but drivers need to know that delays of up to 20 minutes are expected,” said Jeffrey Wallace, DOT’s construction manager on the project.
“We’ll do our best to get the roadway cleared and reopened to traffic as quickly as possible following each blast, but we also need drivers to know that delays are possible so they can plan their trips accordingly,” he added.
A variety of work is planned, depending upon existing roadway conditions and the types of improvement called by the project’s design. Some areas will receive a new roadbed while others areas may only need to be repaved. Alignment, drainage and safety improvements will also be made at various locations.
The portion of the project south of the Eustis Post Office will include widening the existing roadway to allow for a four-foot shoulder. The remainder of the project will provide 11-foot travel lanes with 3-foot shoulders.
Wallace also noted that because of the difficulties involved in ledge excavation and drainage pipe installation, traffic through the project area will be restricted to loads that are 10 feet wide or narrower.
The contract for the project, awarded to BridgeCorp of Augusta on a bid of just over $9.7 million, calls for completion of the project by mid-November 2006.