FARMINGTON – Although some recent tests showed unacceptable toxicity levels in Farmington’s wastewater treatment plant’s outflow, there does not appear to be a malfunction in the plant’s operations, according to Steve Moore, wastewater superintendent.
“I think we’ve determined that the plant is working right,” Moore said Friday.
Though most recent tests have come back fine, toxicity levels killed fish larvae used to test the wastewater during the weekend of Sept. 24. Moore is waiting for test results that will determine the exact chemicals causing the toxicity. There are hundreds of possibilities, he said.
Because the toxicity levels rise only on particular days, Moore believes someone is illegally dumping into the sewer system and suspects it is a commercial entity. Once tests determine what chemicals are causing the problem, the town will need to trace incoming lines to determine their source.
Mandates from the Clean Water Act now require the town to treat its outflow to chemically remove phosphorus from it – something noted in fine print in the town’s most recent two-year license. Wastewater was supposed to be treated from June 15 to Sept. 30, but Moore missed the change in the license, which is due to expire in November. He only began treatments this year. That could cost the district a fine from the Department of Environmental Protection, but Town Manager Richard Davis hopes state authorities will forgive the oversight. Representatives from the DEP did not return telephone calls Friday.
“I didn’t mean to, but I missed it,” Moore said admitting his error.
The superintendent’s job, which he has held for 32 years, has gotten much more complicated. The plant only needed to remove solids in the past. Now, workers have to treat with chemicals, he said.
The $1.1 million budget, funded by user fees, has remained fairly stable for awhile, Davis said Friday. The cost for the new chemical treatment is about $25,000 annually, according to Moore – about 3 percent of the total budget.
“Hopefully, we can save somewhere else,” Davis said. “We will juggle things around to keep rates stable, and if there were to be an increase, it would be very, very small,” he added.
An electricity management device recently installed at the plant is projected to save “a considerable amount” of money, though Davis did not know exactly how much.
Comments are no longer available on this story