KINGFIELD – How the Planning Board should define the word “constructed” as it appears in town ordinances was the subject of lengthy discussion Wednesday night.
On the first night of Planning Board deliberation on Poland Spring Water Co.’s application to build a bottling plant in town, discussion centered on how the board will regulate the two parts of the projected operation: bottling and bulk water pumping.
Poland Spring officials have said all along they plan to use the site of the proposed $60 million to $80 million plant primarily for pumping, and then bottling spring water from Kingfield and surrounding pump sites. They also say there are plans to truck some bulk water out of town to be packaged in the company’s other plants in Hollis or Poland.
In fact, truckloads of Poland Spring water are already making their way through town from nearby pumping stations.
The issue for the town is clear cut. Kingfielders have said at meetings and when they voted on ordinance amendments earlier this year that they are opposed to a pump-and-run sort of operation, which would bring no money or jobs into town.
Residents voted wording into the town’s zoning ordinances specifying that, while pumping and trucking water away is acceptable to a point, any aquifer dependent industry given a conditional use permit must have constructed a bottling facility one year after a permit is given.
Planning Board members worked on additional wording Wednesday that would prevent Poland Spring from taking advantage of the permit and only using, for example, one bottling line, and trucking out the rest of the water permitted.
It’s not that the board doesn’t trust Poland Spring, exactly, Planning Board Chairman David Guernsey explained. “We’ve been told to view this as it may not be Poland Spring forever,” he said. The bottling company’s parent corporation, Nestle Waters North America, might sell the plant, he suggested. “That’s why we don’t want to do things on a handshake.”
Numbers, rules and percentages of water being withdrawn for the two different purposes were thrown about, but throughout the discussion Poland Spring engineers and lawyer Phillip Ahrend worried about restricting the operation too much.
It’s important to word the permit so the town’s protected, but with enough leeway so Poland Spring can still do business in a reasonable way if there’s a fire, for example, they said. The company also wants to be able to truck more bulk water than they’re bottling in Kingfield in the time after the permit is given, but before the operations at the plant are up to speed, Ahrend said.
Ideas were still being tossed around late Wednesday evening.