LEWISTON – Less than two months after it launched a capital campaign to finance a new home, the local Chamber of Commerce is well past the midpoint of its goal.
Androscoggin County Chamber of Commerce President Chip Morrison had issued a challenge at the group’s May 12 breakfast meeting to raise $500,000 to help renovate the old Pontiac building at the city’s Southern Gateway. The 100-year-old building – once home to a Pontiac dealership – is intended to become a one-stop business service center by bringing the Chamber, the Lewiston-Auburn Economic Growth Council and the Lewiston Development Corp. under one roof.
“At this time, we have commitments for $360,000,” said Morrison recently. “People have been fabulous.”
A team of 50 volunteers has been leading the effort. It got a boost from an early June phone campaign that raised about $14,000. Since then, volunteers and Morrison have been knocking on doors, making presentations and tapping the resources of its 1,225 members to raise the money.
“People have been quite generous,” said Morrison, noting more than 90 percent of the pledges have come from chamber members.
The projected cost to renovate the city-owned brick building is $2 million, although tax credits for restoring historic buildings could bring that figure down, said Greg Mitchell, assistant city administrator.
The three groups will share in a condo arrangement of the space. For the chamber’s $500,000, it will take the first floor for offices, and meeting and display space. The growth council is expected to raise $500,000 and occupy the fourth floor, providing space for itself, as well as the Maine International Trade Center, SCORE and other state or federal business assistance programs.
The Lewiston Development Corp. will take the second and third floors and develop them to lease. The cost to renovate those two LDC floors doesn’t include fit-up for future tenants, so its portion of the project is $325,000. Mitchell said the space will likely be leased to financial institutions, insurance companies or other businesses that target commercial customers. Those leases will help cover the remaining renovation costs.
The City Council voted to make $1.15 million available as a loan, if the three groups need it. Morrison said he expects the chamber to make its goal and does not expect to tap any city money.
“Our intent is to make our section totally private,” said Morrison.
The growth council is exploring loans to finance its portion of the renovation and the LDC is in the process of lining up tenants, whose lease payments can be used to pay for its portion. There’s about 1,000 square feet of space on each floor.
Naming rights for the building are still available for a $100,000 donation. Morrison said he hopes the chamber will complete its campaign soon. Crews have already begun cleaning the interior of the building and work will continue through the summer. It should be finished by early 2006.
Comments are no longer available on this story