LIVERMORE — Officials will meet with Scott Braley of Plymouth Engineers at 2 p.m. Tuesday, March 1, to discuss design options and costs for a sand and salt shed.

The meeting was requested after Braley’s estimate for an arch design came it at $400,000, or $100,000 more than expected. He said in a recent email to Administrative Assistant Carrie Castonguay that changing a few design decisions could cut costs.

Based on information provided them, selectpersons chose to go with an arch design. A new design would be an additional expense.

Livermore is on a list of Maine municipalities that have salt leaching into the ground, and if it doesn’t build a shed it will lose its contamination waiver and be required to get a DEP license.

Selectpersons have approved applying for a low-interest loan of $400,000 from the Maine Department of Environmental Protection to pay for the shed.

The Maine Department of Transportation will reimburse the town about 37 percent of the cost of the shed, if it submits a preliminary plan in June.

Advertisement

Administrative Assistant Carrie Castonguay said if the town chooses not to use the state programs, Livermore would not be eligible for the 1.5 percent loan.

To qualify for state help, the town must also have an engineer design the shed.

Selectperson Tom Gould said the town can’t miss the state’s requirements on watershed protection. “We need to be protected in the future,” he said.

Board of Selectpersons Chairman Peter Castonguay said the cheapest option is a fabric building. Even if the building fell down in 20 years, the ground work and cement would still be there, he said. 

At the town meeting in June 2015, a straw poll showed voters were not in favor of a fabric building.

Selectperson Mark Chretien suggested bringing at least two options to the town meeting. 

Advertisement

Exact costs can’t be determined until the project goes out to bid.

The board had hoped to put the shed out to bid in February or March. The loan application is also on hold for another month. Treasurer Amy Byron said March and April are the only options she knows of for applying for the loan.

The plans must be submitted to the state for review by July 1, 2016. Construction must be finished by July 1, 2017.