ARCADIA, Fla. (AP) – A public shelter that collapsed with 1,400 people inside during Hurricane Charley was reportedly built following minimum or subpar building standards, a newspaper investigation found.

The two-year-old Turner Agri-Civic Center was supposed to withstand winds of at least 140 mph. The metal roof lifted off the building and its east wall toppled in winds estimated at 89 to 110 mph; there were no serious injuries.

The News-Press of Fort Myers reported Sunday that although DeSoto County saved $260,000 on the $8 million building project, it spent extra for custom accent paint colors, to install bronze plaques and to buy a better flagpole.

The county used a low-bid contractor, Trident Building Systems Inc., that lacked certification that would have allowed experts to inspect the design and provide quality control, the report found.

It also failed to upgrade construction materials or use the latest in disaster-resistant design.

Officials for the county, construction manager and the contractor who built the metal frame and roof declined to comment.

“We put Trident through a very intensive investigation,” said David Titsch, president of building architect Titsch & Associates, Architects. “We wouldn’t have let them build the building if we weren’t satisfied.”