AUBURN — When crews button up the pavement around the Western Promenade neighborhood later this summer, they’ll finish up the last big storm-water separation project in the city.
“What we do next is a few isolated streets, some basins here and there,” said Sid Hazelton, district engineer for the Auburn Sewer District. “They’re scattered all over town, so we’ve lumped them all into a project by themselves.”
It’s taken 12 years and millions of dollars to get to this point. Crews started the Western Promenade project last fall. This week, they’re digging up the road between Gamage and Beacon, building a parallel sewer system that will drain storm runoff directly into rivers and streams.
Next, they’ll move to Holly Street and Western View.
Auburn, like 47 other communities in Maine, was built with combined sewer systems. Household and commercial sewage flow through the same pipes as those carrying water from the storm sewers. All of it is carried to the Lewiston-Auburn Water Pollution Control Authority before it’s released into the river. Heavy runoff can overwhelm the system, flushing excess storm water and raw sewage out of access points along the river.
“We’ve had some neighborhoods where it didn’t get flushed into the river or into the sanitary sewer,” Auburn Sewer Superintendent John Storer said. “It backed up into people’s basements.”
In 1994, federal law required those cities to build parallel storm-water systems that carry storm water directly to the river.
The Auburn Sewer District and the city of Auburn in 1999 began working on a 15-year project that called for $19.2 million worth of work to build the parallel system and eliminate 11 combined outflows.
According to state records, 102.3 million gallons of storm water overflowed Auburn’s system in 2000 and overflowed into the Androscoggin River or its tributaries. By 2006, that number was down to 28.9 million gallons. By 2010, it was down to 12.9 million.
That number will come down even further once the Western Promenade project is finished, but Hazelton said it would be some time before all of the work is done.
“It gets a bit more difficult from this point on,” he said. Not only are the remaining storm-water connections isolated, but the city will have to track down and seal any leaks or illegal household drains.
“That all could take awhile still,” he said. “It’s harder to target those because we don’t know where they are exactly.”
Hazelton said the district could begin an engineering study to locate leaks. That could involve sending remote television cameras into the sewer system or pumping the pipes full of smoke.
The end of the project will be a “true milestone,” Storer said. “By the end of this summer, we will really be able to tell people we really should not have those problems any more. The hard part is that people don’t see what we’ve built because it’s all underground. But the end result is a cleaner river and no back-ups into people’s homes.”
In Lewiston, crews will spend at least five years building a parallel storm-sewer system in the Jepson Brook watershed, according to Public Works Director Dave Jones.
“We started the first phase of that project, and that’s going on right now,” Jones said. “The second phase goes out to bid this summer. It’s a long-term project.”
Like Auburn, Lewiston began working on a 15-year plan to remove combined storm and sanitary sewer systems in 1999. But Lewiston’s task has been bigger than Auburn’s because Lewiston had an estimated 30 storm-sewer outflows, compared to Auburn’s 11.
In 2000, storm-water overflows sent 136.9 million gallons of combined runoff and sewage into the Androscoggin River. In 2006, it increased to 159 million, then decreased to 90.9 million 2007. It increased to 152 million in 2008, then went down to 116 million in 2009 and 113 million in 2010.

Comments are no longer available on this story